Milestones and roadmap
The LokiCheckout consists of numerous Magento modules, each with its own version (following semantic versioning standards) and its own project management. To keep track of changes, the milestones on this page are used.
|
Timeline |
Status |
Goals |
Progress |
| Milestone 0.1 |
August 2024 to April 2025 |
completed
|
13/13 done
|
100%
|
| Milestone 1.0 |
April 2025 to May 2025 |
completed
|
10/10 done
|
100%
|
| Milestone 1.1 |
May 2025 to March 2026 |
open
|
4/16 done
|
25%
|
| Milestone 1.2 |
April 2026 to July 2026 |
upcoming
|
0/2 done
|
0%
|
| Milestone unscheduled |
- |
upcoming
|
0/8 done
|
0%
|
Milestone: 0.1
Date: August 2024 to April 2025
Status:
open
13/13 done
(100%)
Milestone: 1.0
Date: April 2025 to May 2025
Status:
open
10/10 done
(100%)
Milestone: 1.1
Date: May 2025 to March 2026
Status:
open
4/16 done
(25%)
Milestone: 1.2
Date: April 2026 to July 2026
Status:
open
0/2 done
(0%)
Milestone: unscheduled
Date: -
Status:
open
0/8 done
(0%)
Milestone 0.1 goals
Automated testing via GitLab CI/CD
complete
GitLab project and repositories
complete
Private composer API
complete
Client-side / Server-side filtering
complete
Client-side / Server-side validation
complete
Milestone 1.0 goals
Milestone 1.1 goals
LokiCheckout Delivery Date
open
WCAG 2.1 AA compliance
complete
Amazon Pay integration
open
Fedex integration
open
Braintree integration
open
Milestone 1.2 goals
Chase integration
open
BePOST integration
open
Milestone unscheduled goals
HiPay
open
Humm integration
open
OpenPay integration
open
AfterPay integration
open
PensoPay integration
open
checkout.com integration
open
GLS integration
open
Big changes (stalled until next major)
- Drop support for PHP 8.1 and 8.2 (and corresponding Magento versions)
- Rewrite
Context classes to reduce dependencies
Last modified: November 17, 2025